The Enterprise Centre

Introduction / summary

A reserved matters approval for the layout, scale, appearance and landscaping for the construction of an Enterprise Centre for Royal Holloway, University of London was submitted to Runnymede Borough Council on 25 March 2019. The development will provide the university with the opportunity to create a regional centre of excellence in the fields of cyber security and big data and will make the EM3 region (focused along the M3 corridor) the natural go-to place for companies who want assistance in developing, testing or validating security products and services. Runnymede Borough Council granted planning permission, subject to conditions, on the 31st July 2019. The university and its design team (Stride Treglown) are currently addressing pre-commencement conditions and enabling works to enable site set up in November/December, with the planned demolition of the existing building scheduled for January/February 2020.

Figure 1: Location of the site within the campus, close to Egham Road


Figure 2: Extract from the Masterplan showing the principle of a building in his position


Relevance to the Estate Plan

The Estate Plan was updated in November 2017 to reflect all recently-completed developments including the student accommodation north of the A30 (George Eliot Hall), the Boilerhouse, Beatrice Shilling Building and Emily Wilding Davison Building. This was sent to the council in an informative manner.

The plan maintained the proposed site for the Enterprise Centre as Plot B06 (see figure above). The schedule of development identifies this site as having the potential for a three/four-storey building providing 5,500sqm of academic or operational floor space. The outline planning application provided detailed approval for the re-positioned Piggery Gate entrance which is located immediately to the east of Plot B06.

  • Figure 3: View looking towards the entrance from within the campus

  • Figure 4: View from Egham Hill showing the remodelled Piggery Gate Junction

Reserved Matters Submission

Runnymede Borough Council granted planning permission, subject to conditions, on the 31st July 2019. The university and its design team (Stride Treglown) are currently addressing pre-commencement conditions and enabling works to enable site set up in November/December, with the planned demolition of the existing building scheduled for January/February 2020.

Timetable

The construction programme is scheduled to last approximately 16 months, with the building becoming operational in the summer of 2021.

The university is currently engaged in a tender process to appoint a contractor to deliver the project.

Link with other Estate projects and plans

The Enterprise Centre is located close to the existing Piggery Gate junction into the campus: this is currently closed to vehicles and provides a pedestrian entrance onto Egham Hill. The 2015 outline planning permission across the campus secured the detailed approval of the remodelling of the junction to create a four-arm movement junction. This will also allow access and egress to that part of the campus north of the A30, close to Sutherland House and Sutherland Lodge. Details relating to the Piggery Gate project can be found here.

The Enterprise Centre is to be positioned on the site of the Orchard Building and the Handa Noh Theatre. These buildings will be demolished to make way for the new building. The activities undertaken within the Orchard Building will be temporarily relocated elsewhere within the campus. The Handa Noh Theatre is proposed to be relocated to a site north of the A30 close to Sutherland Lodge, where the Department of Drama, Theatre and Dance is located. Details relating to the relocation of the Handa Noh Theatre can be found here.

The Enterprise Centre proposal sits opposite a new academic building identified for the Eastern Gateway Building. This project is at an early stage: a client brief is being developed to enable designs to progress and be tested. This project is being delivered in accordance with the general principles as set out within the Estate Plan. Designs remain to be progressed and a public exhibition will follow later in the year. Project details will be updated here.

Please take the time to download and take a look at the exhibition board. We trust that you will find these helpful.

Download (July 2019 Boards)
Download (Sept 2019 Boards)

If you have any comments in relation to the emerging project, please complete the following survey.

View Survey

The university has agreed to extend the period by which online responses can be submitted. The survey will remain open until midnight on the 13th October. If you have supplied comments, you do not need to complete the form again. The link provided will take you to a copy of the September consultation questions. This link is provided as we understand certain individuals experienced difficulties in submitting comments during September.

If you wish to make additional comments on any development project being promoted by the university, please email these to consultation@stridetreglown.com

Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from Youtube
Vimeo
Consent to display content from Vimeo
Google Maps
Consent to display content from Google